NJ solar project
faced severe weather—and an earthquake
While
building the 10 MW New Jersey Oak Solar project, Lincoln Renewable
Energy ran into some big time weather including Hurricane Irene,
followed by a snowstorm in October—and an earthquake.
By
Diane Mettler
What is special about the New Jersey Oak Solar project in Cumberland,
New Jersey's Fairfield Township? For starters, the 101-acre site
contains 53,200 fixed solar panels, produces 10 megawatts of AC power
(enough energy to support 775 homes), and is the largest
non-utility-owned solar project east of the Mississippi, according to
Lincoln Renewable Energy (LRE).
Back in 2009, LRE was looking at two primary markets for
solar—California and New Jersey.
"We felt at the time that the California market had significantly more
competition for utility scale solar than New Jersey, so we started our
greenfield development in New Jersey. It was our first area to
develop," says John Stone, vice-president, project management at LRE.
Macquarie Energy LLC entered into a long-term purchase agreement for
the power and renewable energy credits from the NJ Oak project and also
provided construction finance and term debt to the project.
Stone, speaking about Mac-quarie says, "I think that there are
different types of customers in the energy marketplace. Some are your
traditional utility offtakers, and some are traditional power
marketers, which I feel Macquarie Energy is. They are into power
marketing and power sales."
The solar project is located off the main highways in Southwest New
Jersey. Although there are a few neighbors close to the project, the
power generation is quiet, and should neighbors come in closer over the
25-year life span of the solar farm, sound won't be an issue.
The site LRE chose was a piece of land that had once been actively used
for agriculture but had since been reclaimed over the years by brush
and trees. "This made it an ideal setting for a solar farm because, in
New Jersey, it's important to make the perimeter of solar sites
visually pleasing and the scrub brush and the mature trees that we left
around the outside provided a natural viewshed."
Although one of the benefits of the location was its vegetation,
clearing excess brush and trees was also one of the challenges. Of the
parcel's 101 acres, 84 acres had to be cleared for the 62-acre plant.
The vegetation that was cleared was recycled and ground up into 47,000
cubic yards of mulch.
"We had to take out about 14 more-mature trees because they caused
either a shade issue to the plant or were danger trees, meaning if they
were to fall, they would fall into the fence or into the plant itself,"
said Stone. "They will be replaced in the perimeter with smaller trees
of like species."
LRE worked closely with Quanta Renewable Energy Services (QRES) and The
Ryan Company (Ryan), both wholly owned affiliates of Quanta Services.
"We hired Ryan on a turnkey basis," says Stone. "They proposed Yingli
modules, and after we did our due diligence and talked to them about
the layout optimization, we agreed. QRES provided the engineering and
procurement and Ryan the construction."
QRES chose the YGE-235 series high efficiency, multi-crystalline
modules, which deliver a module efficiency of more than 14 percent.
"Ryan and QRES had worked with these modules before and understood the
racking systems required and the installation processes, so we felt
that Ryan would bring a more efficient construction effort," adds
Stone. "And because they had done the engineering, they knew how many
modules to put in strings and how to optimize the layouts."
LRE also chose Satcon Technology Corporation inverters, based on QRES's
recommendation. Satcon delivered ten 1.0 MW Prism Platforms configured
with the company's Equinox inverters.
Satcon says that the Prism Platform is its turnkey utility-grade
multi-megawatt building block, complete with factory-integrated step-up
transformers, MV disconnect switches, and power-conversion electronics.
LRE broke ground in July 2011 and had no idea what kind of challenging
weather they were in for. In August, Hurricane Irene blew through and
it was followed by a snowstorm in October. If that wasn't enough, the
New Jersey site experienced an earthquake as well.
|
|
|
The 101-acre Oak Solar site
contains 53,200 fixed Yingli solar panels and is the largest
nonutility-owned solar project east of the Mississippi, according to
Lincoln Renewable Energy.
|
|
|
Luckily, when Hurricane Irene came through, there were no modules on
site, and the Ryan crews worked to make sure everything that could
potentially fly around was tied down.
Because you can't dictate what Mother Nature is going to throw your
way, Stone says it's important to build extra days—"float
days"—into the schedule. "We certainly did that and still
worked six and seven days a week for the last couple of months to make
up some of the time."
When construction was at its peak in
November, there were 145 workers
on site, with Ryan's subcontractor using IBEW Local Union 351
electrical workers for electrical portions of the project. The schedule
called for workers doing final onsite clean-up for six months following.
In the end, despite the dreadful weather, the project came in on
schedule. And with some accelerated commissioning items required
because of weather delays, the construction also came in on
budget—$41 million.
In mid-December 2011 the testing of the solar project was complete.
With the construction and weather difficulties behind them, everything
was working well.
The Clarity Monitoring System by Solar Power Technologies (SPT) will be
installed during the first quarter of 2012. SPT and LRE are working
through some of the preliminary design decisions.
LRE will monitor the site productivity via the Internet using ArgusOn.
"They are an SPX company, and they are doing our remote monitoring from
Franklin, Tennessee," says Stone. "They monitor the plant on a daily
basis, updating it every 15 minutes, providing Ryan (who is also the
O&M Contractor) and us with periodic production and status
updates."
"SPT intends to bring a better monitoring solution that will provide
better efficiencies for the solar plant," says Stone.
At 10 MW, the New Jersey Oak project is the minimum size for
LRE—10 MW being the floor and about 50 MW being the ceiling.
However, Stone says they might build bigger projects than 50 MW if the
conditions were right. "We have to have absolutely the right land and
the right energy offtake. It's all dependent on the financial modeling
and other project components."
With the New Jersey Oak project, LRE's finance team already had a
history with Macquarie before going into the project. Stone says that's
key. "In the finance business, it's all about relationships. Our
vice-president, finance, had discussions with Macquarie and found that
they had an appetite to buy some solar energy, and we, in turn, had a
project that fit the locale that they wanted to buy the energy from.
The timing was right, so the deal came together."
LRE's development team now has greenfield projects in 13 states. The
company is continually looking for the right packages, which includes
the right land, customers, and financing, among other things.
Looking into the future, Stone would like to see a national energy
policy that's got some strength to it. "I think we need a national RPS
that will help some of the other states get on board with renewable
energy. But even so, I think the solar market is going to become more
robust. I think as prices continue to come down on modules, there's
going to be more appetite for solar energy."
Although there were challenges during the project, LRE says that the
people of Fairfield Township definitely weren't one of them.
"They had some very exacting requirements, which we were able to meet,"
says Stone. "In fact, they are now using our package as a benchmark for
other companies that are developing in this area."
Some of the Township's concerns centered on environmental issues. For
instance, they required a 10-foot fence to keep deer out of the area
and also infiltration basins around the site so that the water from the
site didn't flow off the site.
"We also created a special grasslands habitat that requires a unique
mixture of grass and field seeds that grow to a maximum height of about
12 inches. But it also supports the small rodents and things like that,
that will certainly be within the plant," adds
Stone.
With the project complete and the plant running smoothly, Stone is
proud of the outcome and his team.
"This is Lincoln's first utility scale project, and I'm particularly
proud of having been able to build this on the timeline and budget that
we established. We had a good group on this project, from the Ryan and
QRES folks, who organized labor on site, through our owner's
representative from Rev1 Services. We all worked together as a team,
and I think without that, we wouldn't have been as
successful."
The team will probably be together again, as LRE and Quanta Renewable
Energy are already talking about future projects.
March/April
2012
|
|