Old school solar
The Catholic University of America in
Washington D.C., along with installation partner Standard Solar, took
on a demanding project integrating a solar power system on seven campus
buildings—one of which is more than a century old.
By
Diane Mettler
In 1889, when the Catholic University of America opened its doors in
the District of Columbia, solar power was what farmers used to grow
crops.
Professors at the time couldn't have imagined that 124 years later the
university would become a beacon for sustainability and house a 682 kW
solar facility, the largest in D.C.
C.J. Colavito, director of engineering for Standard Solar, which
handled the solar installation, says integrating a solar power system
onto seven campus buildings—one of them more than a century
old—was technically complex, requiring a variety of skills and
different types of technology, but it was also incredibly satisfying.
"Catholic University has a very targeted sustainability effort, and
they're one of the few customers whose main reason for installing solar
power is not to save money," he adds. "The primary reason is to be more
ecologically friendly and to support the student body's demand for
green energy and a more sustainable campus."
Like many projects, it started with solid relationships. Standard Solar
had a relationship with Washington Gas Energy Systems, the larges
electricity supplier in the state of Maryland and Washington D.C. Both
Washington Gas and Standard Solar had existing relationships with
Catholic University.
"When we brought Washington Gas in as our system owner/PPA provider, it
went together very smoothly," says Colavito. "It also helped that
Catholic University has a very smart and politically savvy energy
manager that really ran the project and pushed it through the
university to get all the proper approvals."
It's a good thing that all the players got along so well because the
three-phase project had numerous and unique challenges.
"One of the most challenging things on the development side was that
the campus has many buildings, and we probably looked at over 30
different buildings to site the solar on for Phase 1, before selecting
the final four that we went with," says Colavito. "We did preliminary
drawings and PV system layouts for over 30 buildings, and we probably
changed them all twice."
When choosing campus buildings, there were a number of considerations
for Standard Solar including:
• Structural capacity. Could the roof support the ballasted PV
system?
• Rooftop condition. Would the roofs hold up for the 20 years the
PV system would be in place?
• Irregular shapes. Would a tall, skinny, or odd-shaped roof
support the rooftop system?
• Building financing. Would the current bonds/financing of various
buildings allow for this kind of project.
"Financing of the building and the contingencies around that financing
invalidated about half the buildings on campus," says Colavito.
Seven buildings were selected to house the total 680 kW of solar power,
and about 90 percent is on three buildings. "That means we had four
buildings that were tiny—not exactly ideal installs. They
required even more project management and engineering effort than the
larger buildings. So it was very challenging," says Colavito.
For Phase 1, Standard Solar selected DuFour Athletic Center (122 kW),
Aquinas Hall (104 kW), Flather Hall (35 kW), and Gibbons Hall (32 kW),
and construction got underway in 2009.
|
|
|
Seven buildings at
the university were selected to house the total 680 kW of solar power,
and about 90 percent is on three buildings. That meant four of the
buildings were small—not exactly ideal installs. |
|
|
Castle-like Gibbons Hall proved to be a challenge, especially in the
beginning, recalls Colavito. "The building is extremely old, has a
large tower in the middle, and no access to the roof.
You had to go up the stairwell in the middle and crawl through a small
window that was only about two feet wide. You had to wiggle through to
get up there, making site visits and development and planning tricky."
Once construction got underway, scaffolding was erected for access, but
there were new issues to address. "We had to push the solar panels out
to the farthest ends of either wing, so they wouldn't get too much
shading from the tower in the middle," explains Colavito. "Because of
the shade, we used four separate SMA Sunny Boy 7000 string inverters to
run that 32 KW system. We have two string inverters for each wing, with
one dedicated to the inside half and one designated to the outside half
of the system so that the shading on the inside portions from the large
tower wouldn't affect the outside as much."
Gibbons wasn't the only building with challenges. Aquinas is an office
and classroom building, and Flather Hall is a dormitory, so there were
security concerns. Standard Solar had to work very closely with the
university and make sure that students weren't disrupted.
"We knew exactly what days were study days, test days, and holidays,
and we did our best to get in and get out without disrupting things,
and we made sure the meat of our construction activity didn't happen
during key times in the university schedule," says Colavito. "It also
helped that the students were very interested and supportive."
For phase one, Standard Solar went with Suntech solar modules. In
addition to the four SMA Sunny Boy 7 kW systems used on Gibbons,
Standard Solar chose Satcon inverters for DuFour—two Satcon 100
kWs and one Satcon 30 kW.
Because of reroofing schedules, the DuFour Athletic Center was the only
building that got additional PV during Phase 2.
"We were only allowed access to one section of DuFour on Phase 1
because that was the section they planned to re-roof immediately. Then
when they re-roofed another section of the building, we went in and
installed another 120 kW," explains Colavito.
Again Standard Solar used Suntech modules but chose Advance Energy
inverters. Advance Energy
makes excellent products that have high reliability and good
pricing—and that's why they worked with them, says Colavito.
Phase 3 wrapped up in 2012, adding an additional 268 kW in Trina Solar
modules.
• An additional 77 kW to DuFour— bringing the total to 319
kW, or half the PV on the campus.
• 11.2 kW on Pangborn Hall, the university's engineering building
• 171 kW on the O'Boyle carport manufactured by Structural Solar
• 8 kW installed on the Grounds Maintenance Complex
Phase 3 had challenges from the start. "We had already cherry-picked
the best buildings of what was available, and we had to get creative,"
says Colavito. "The university was also more interested in getting some
token systems for demonstration and for solar to be on some key
buildings."
An example was the ballasted roof mount system on Pangborn Hall. "11.2
kW is a very small system, especially in a commercial setting. We
wouldn't have been able to do a job that small if it wasn't rolled in
with three other sites."
|
|
The Grounds Maintenance Complex has
a standing seam metal roof and was originally supposed to be 26 kWs.
After a structural analysis, engineers would only allow 8 kW, but
Standard Solar made lemonade from lemons.
"We put in two nice, clean rectangular blocks on the roof, and it
complements the Grounds Maintenance Complex nicely," says Colavito.
"Unfortunately for us, it cut the project down in size and made it more
difficult to do, but because Catholic University is a partner of ours
and so is Washington Gas, we just rolled with it and re-designed the
array and figured out how to make it all work."
On both the Grounds Maintenance Facility and Pangborn Hall, Standard
Solar used Power-One, three-phase, 10 kW string inverters. "There were
only a few companies at the time when we were first designing these
projects that offered a true three-phase string inverter."
Financing also became more complicated by the three-year project span.
"The renewable energy credit markets, the electricity markets, and the
cost of PV systems changed drastically between 2009 and 2012," says
Colavito, noting that the DuFour building, which was part of each phase
was especially unique.
"Each time we added solar power to a building, it was a completely
different PPA rate with a completely different contract between the
system investor and Catholic University. So we have three separate
inverters for a 300 kW system."
The design was complex.
"Each inverter output needed to be separately revenue grade metered and
separately monitored because they were all built differently," says
Colavito. "In the case of DuFour, we were going back and undoing some
of the work we had done to upsize it and re-do it again."
The parking lot required a charging station, but not before the removal
of several light posts to put up the solar array. "We then replaced
that lighting with LED undermount lighting on the bottom of the canopy.
Also, the parking lot isn't flat, and it has multiple orientations of
the array."
Standard Solar participated in several student outreach programs during
the three years. "I personally gave tours to engineering classes and
renewable energy classes of the solar power systems during and post
construction. Standard Solar, along with Washington Gas, also supported
and sponsored a solar picnic table design competition."
The picnic table is definitely a statement. "It has integrated
batteries, a little monitoring system with charge controller and
inverter to supply AC loads. It's also got some flexible thin film
modules that adhere to the top of the awning on the picnic table," says
Colavito. "I can't say it was easy to manage and build, but we made it
work, and it was important to the university."
Now students can sit and eat outside the main student center, while
charging iPhones, laptops, and other mobile devices.
The student support has led to Standard Solar sponsoring the solar
decathlon team, which will be the first such team for Washington D.C.
universities.
The project also resulted in a couple of interns and a new hire at
Standard Solar. "That student was on one of my first tours in 2009,"
says Colavito.
The ribbon cutting ceremony this past September wasn't just a
celebration of a successful 2,600-panel PV solar facility, but also of
creativity, dedication, and teamwork.
Colavito says he's proud that Catholic University is a
‘three-peat' customer. "I think that speaks volumes." And the
university professors from 125 years ago would be impressed too.
January/February
2013
|
|