New solar farm delivers power–and R&D results
Schneider
Electric's dual 600/1,000-volt solar farm—the first such
facility in the U.S.— was built as a test lab to develop
components for sustainablesolar farms and help the company optimize its
inverter design and PV solar applications.
By
Diane Mettler
|
|
Aside
from copper wire and the approximately 3,500 solar panels and racking,
the solar components on the Smyrna project are all made by Schneider
Electric. The project is one of the three largest solar farms in
Tennessee, producing enough energy to cover, on average, 25 percent of
the energy consumed at the Schneider Electric facility. |
|
|
|
Research and development facilities are often considered a necessary
expense. But what about an R&D facility that not only conducts
testing, but showcases new products and generates revenue?
This
is the case with Schneider Electric's 1-megawatt solar farm located on
six acres in Smyrna, Tennessee. It's a dual voltage—600DC and
1,000DC—solar farm, the first of its kind in the United
States, and it was built as a test lab to develop components for
sustainable solar farms and help Schneider Electric optimize its
inverter design and PV solar applications.
If
that wasn't enough, it is one of the three largest solar farms in the
state, producing enough energy to cover, on average, 25 percent of the
energy consumed at the facility.
It's
surprising there aren't more dual voltage solar farms out there. Global
companies, like Schneider Electric, provide solar components to
companies that run on either 600 or 1,000-volt systems.
"In
the U.S., we produce power with 600 volt systems. In Europe, many of
those systems are 1,000-volt systems with fewer connections and
everything that goes with a higher voltage system," says facility
manager Edwin Willhite. "This solar field is configurable between 600
and 1,000 volts, so that it can be operated as a working lab. We can
demonstrate our own products, like inverters, DC switchboard, and DC
switches, to a U.S. market that's not as familiar with the 1,000 volt
market."
Aside
from copper wire and the approximately 3,500 Suntech solar panels and
racking, the solar components are all made by Schneider Electric. For
the company to switch the solar field configuration from 600 to 1,000
volts and back again is relatively easy.
"The
panels remain the same, it's the configuration box out in the field
that changes," says Willhite. "It's essentially a matter of
disconnecting or changing four bolts, turning a plate around, and
putting those bolts back in."
During
the design and construction, creating a safe process for future users
was of utmost importance. "We did a lot of work to ensure we could
isolate and provide the right amount of safety for our operators and
technicians when they make those kinds of changes," adds
Willhite.
When
the solar farm went live, it began simultaneously running and testing
the 1,000-volt inverter. The solar farm will run at 1,000 volts for a
period of time, and when the operators are satisfied with tests
results, they will move on to something else. Creating energy is almost
a byproduct.
Since
Schneider Electric makes a wide range of products for a global
market—residential to commercial—there won't be a
shortage of products to test.
The
price tag for the solar field came in at $6.25 million. Willhite says a
percentage of the amount went toward the cost to build a traditional
solar field, and part went into the R&D component.
Testing
facilities are expensive because of added technology. For example, the
dual voltage solar field required three different grounding grids. "It
has a positive, a negative, and a no ground or floating ground. So we
have three times the amount of copper for grounding than we would
normally have because we have different kinds of grounding systems. We
also have additional switches—part of our safety design,"
explains Willhite.
"Making
the field configurable for either voltage or grounding, and being able
to accept the power in whatever configuration we may choose to use is
complex. Credit goes to our own Schneider services group that did the
design."
It
took Schneider Electric approximately 15 months to complete
construction after partnering with TVA's (Tennessee Valley Authority)
solar generation program. "We signed the agreement with them the middle
of
August of 2010. After that we had about three months of pre-work before
we began construction," says Willhite. "It was an incredible team
effort, not just with TVA but with many different divisions and parts
of Schneider Electric."
Hundreds of individuals were involved during construction, and about 50
people were out in the field for months. It also required a lot of
patience and understanding from the employees at the Smyrna facility
when roads shut down during construction, among other things. "When we
needed help, they came and pitched in to help," says Willhite. "They
were a big part of that team as well."
Schneider Electric got to put its facility to the test immediately. The
field went online on July 25th, followed by days of triple-digit
temperatures.
"Our solar field was operating at full capacity, and we were putting a
megawatt back on the grid, at the same time our local utility was
asking other customers to lower their load," says Willhite.
"It was satisfying to use this testing facility to help generate
renewable energy and help with grid issues," he adds. "I could look at
the dashboard and see we were really making a difference."
The power generated at the solar plant is equivalent to 25 percent of
the power needs at Schneider Electric's Smyrna facility. Currently
though, they are selling the power to the local utility and buying it
back.
Although the solar field has run smoothly from the start, like any
other first-of-its-kind project, it came with its own unique challenges.
Bill Brown, the Schneider Electric engineer for the project, had his
work cut out for him from the start. "Bill was not only designing and
getting specifications so that we could use Schneider products, but
some of those Schneider products had not been developed yet," says
Willhite.
"To make it work, we were developing new products, getting them on time
and getting them ready to work by dates we'd scheduled way in advance
of their development. It was a real engineering challenge."
One of the new products that had to be incorporated were the combiner
boxes, which collect energy from the panels. "The combiner boxes move
up to progressively bigger boxes so that you consolidate the power
coming from those boxes to go to the inverter," explains Willhite.
"We also had a brand new DC switchboard to help manage the power into
the inverter from those boxes. The configurable box where we can change
from 600 to 1,000 volts was also new."
|
|
The Schneider
Electric facility is a dual
voltage—600DC and
1,000DC—solar farm, the first of its kind in the United
States. It was built as a test lab to develop components
for sustainable solar farms and help the company optimize
its inverter
design and PV solar applications. |
|
|
|
With all these challenges the
ribbon-cutting day was more than just a
formality, it was the satisfaction of a job well done. It was a
100-degree day, and attendees could see the field working at full
capacity.
"You could see first-hand that with our ever-growing energy demand, we
were part of the solution," says Willhite.
When the facility isn't doing research and development, it runs just
like any other solar farm. It requires little maintenance and Schneider
Electric can monitor activity remotely.
"I can be in North Carolina, call it up, and look at how the facility
is performing and operating from my desktop," says Willhite.
By selling the energy produced to the local utility, the one-megawatt
farm will pay for itself in approximately eight to nine years.
"However, when we consider what we're getting in terms of product
development, design, testing, and marketing, our payback should be much
shorter than eight or nine years," says Willhite.
Many renewable energy companies have to educate local communities and
convince them to install their facilities. That wasn't the case with
Schneider Electric.
First, the solar farm was built within an industrial park, so there
weren't many of the building issues new projects run into.
"The solar field is adjacent to a local greenway," says Wilhite. "There
is a walking trail that covers roughly two sides of the solar field,
and our local municipality has given us permission to put a sign out on
the greenway that explains what we're doing, what it means to the
community, and how it contributes to the greenway."
Second, the project has generated both excitement and interest.
Actually, the better term is overwhelming interest. Schneider Electric
receives an average of one request per day to tour the facility.
Requests are coming in from the Boy Scouts to the local college, and
from customers to suppliers.
"We even had a local college ask if they could bring out classes every
quarter," says Willhite. "Right now, we are trying to set up a protocol
so that we can accommodate them. We want everybody to come see us, and
we want everybody to go home and talk about solar power."
Besides being a large, cutting edge solar facility, the Schneider
Electric tour has a bonus feature. "We have also developed an electric
car charging station for cars like the Nissan Leaf. And we have
installed four Schneider Electric EVlink
charging stations onsite, so that's generated some curiosity
too."
Even though it was a challenge to develop something that had never been
done before, Willhite said it's been a lot of fun. "Energy efficiency
is in our DNA. We help companies and consumers' organizations manage
their energy better. We believe that energy efficiency is the best step
towards a more secure energy future."
November/December
2011
|
|