Walking toward solar power in Florida
PSEG Solar Source has taken its solar
power projects to the next level with its 15 MW solar farm in
Jacksonville, Florida, which the company sees as the next step in their
"crawl, walk, run" philosophy.
By
Diane Mettler
"We have a crawl, walk, run philosophy in terms of solar power
development," says John Westphal, PSEG Solar Source project manager.
And he sees the company’s new 15 megawatt (MW) Jacksonville solar
power project as "walking" on the way toward a sprint.
"Projects like this help the industry learn how to build bigger
projects, which overall reduces costs, with larger economies of scale,"
says Westphal.
The Jacksonville project began—like many utility scale solar
projects—with a Request for Proposals, by the Jacksonville
Electric Authority (JEA) in 2008. juwi solar Inc. was awarded the
contract in early 2009 and approached PSEG as a potential equity
investor and owner of the power purchase agreement.
juwi handled the fairly rigorous site permitting process with the City
of Jacksonville—with JEA’s support. By October 2009,
construction was underway.
By April 2010—in just a little over five months—the first
SMA inverter was energized. By mid-May, eight of 20 inverters had been
energized, and on September 30, the solar farm went into full
commercial operation.
Energizing inverter by inverter may be a little more time consuming,
but Westphal says with a project of this size, that’s the
preferred way to do it.
You can’t construct a project of this size without a few
challenges, though. In this case, a high groundwater table was one
issue to overcome.
"We’re located close to some wetlands and had to be very careful
about how we handled the groundwater, and we made sure we didn’t
affect any of the wetlands," says Westphal.
|
|
|
PSEG selected a fixed-tilt
racking system over a tracking system, based on an engineering
economics study done early in the project. The Schletter racking system
they selected provided a great deal of pre-fabrication, so that it
could be installed with minimal effort in the field.
|
There was extensive permitting required and construction contractors,
Miller Electric Company and J.B. Coxwell, handled the issues
effectively by laying a system of underground pipes (called "dewatering
socks") at key locations on the site. These pipes made it possible to
pump the groundwater down from specific areas when required.
Westphal says he’s proud that the project came in on time and on
budget. "It gives us more knowledge, experience, and confidence to go
ahead on larger projects." Or in other words, go from walking to
running.
There were a number of reasons why this project went smoothly from
start to finish. First, PSEG and juwi were able to take advantage of
local talent.
"The tools and techniques required to construct these plants can be
handled by a qualified electrical contractor, who may have never built
a large solar plant before. This is because it requires the same
techniques: pulling and terminating wires, installing electrical
equipment, etc." explains Westphal. "It’s the same things
they’d encounter in any other power generation or large
industrial project. And in those areas where they do need some specific
guidance, juwi is an expert."
PSEG also took advantage of innovative technology that made sense for
the project—like First Solar panels.
Westphal says they went with First Solar for several reasons. "First,
there was the cost. They are—per watt installed—a very
cost-competitive solution. Also juwi has a long-term relationship with
First Solar and are able to leverage that relationship into a very
economical package. Lastly, they work better in diffuse sunlight, which
you get some of the time in Jacksonville."
PSEG also chose a fixed-tilt racking system over a tracking system,
based on an engineering economics study done early in the project. "A
tracking system adds a lot of cost. You get more energy out of it, but
we have to evaluate that against the added cost," says Westphal.
The Tucson-Arizona-based Schletter racking system provided a great deal
of pre-fabrication, so that it could be installed with minimal effort
in the field. "Besides going together very quickly, it also gave us a
lot of room for adjustments," adds Westphal.
The process of going from crawling to running is sped up with
incentives. Unfortunately, this particular project—which came to
about $158 per megawatt hour, about twice that of
coal—didn’t come with many.
"The federal investment tax credit is the primary incentive," says
Westphal. "There were also some federal tax rules on depreciation,
which benefit capital projects like this as well." But in Florida,
there is no renewable portfolio standard or additional incentives for
solar.
Financing was handled by PSEG, and the project will provide returns
through a long term power purchase agreement. "The Jacksonville
Electric Authority is purchasing the electricity and all of the solar
credits. And they’re buying them at a price that’s
sufficient to make the project economical from our perspective," says
Westphal.
He adds that learning to finance projects of this size is all part of
the "crawl, walk, run" philosophy. It helps the industry as a whole
learn how to create bigger and more profitable projects in the future.
Although the modular nature of the Jacksonville system is fairy unique,
juwi applied a process they’ve frequently used in Europe.
"It starts with how they install the racking system, how they apply the
modules to it, and how they package the inverters and transformers
inside a prefabricated power station," says Westphal. "It all gets done
in the factory and is then shipped out to the site so that
there’s minimal fieldwork.
All of these characteristics make it both innovative and
cost-effective. And because of that, you’re likely to see more of
that kind of construction in the future."
|
|
Jacksonville Solar is owned by
PSEG Solar Source LLC and consists of approximately 200,000
photovoltaic panels on a 100-acre site. juwi solar, Inc., a
Colorado-based developer and turn-key installer of solar power plants,
provided the engineering, procurement, and construction services.
|
|
|
|
No one wants problems to happen, but planning for them is part of the
juwi system as well. Should a problem crop up, it can be handled both
quickly and efficiently. JEA would contact the owner PSEG, who would in
turn contact juwi—hired to operate and maintain the facility for
the first two years.
"We also have remote monitoring," explains Westphal. "We have secure
websites we can access that tell us how well the plant is doing versus
how it theoretically should be doing, given the weather conditions at
the time. It’s pretty sophisticated stuff."
PSEG can measure the performance of each of the 20 inverters remotely.
Each inverter has a benchmark given the weather and the light. If an
inverter is not performing the way it should—if it’s
falling short—juwi can then dispatch an electrician and a
technician to go out and troubleshoot. "They can even reset some things
remotely, if necessary," says Westphal.
But what about something big—like hurricanes—not unheard of
in the Jacksonville area?
"Although hurricanes are possible at this location, they’re not
that frequent in the Jacksonville area," says Westphal. "We are about
20 miles inland from the shore so we don’t have to worry about
storm surges and that type of thing."
High winds have been taken into account, and the panels are more
durable than they appear. They are designed to withstand a whole slew
of environmental conditions, including golf ball-sized hail and 105 mph
winds.
With the solar farm performing well, PSEG is stretching its legs to
speed up its walk to a run. The company is currently developing a
number of projects throughout the U.S. in the medium to large range.
"Our first two-megawatt projects were kind of a crawl
phase—getting familiar with the technology and the construction
aspects," explains Westphal. "The Wyandot, Ohio, and Jacksonville,
Florida, projects—12 MW and 15 MW—are part of our walking
phase and allowed us to improve our expertise. The run phase will be,
hopefully, significantly larger."
PSEG is optimistic about the potential market, particularly the
utilities sector. The company expects to see continued growth, with
accelerated growth in three to five years.
"The solar industry has made a lot of strides in driving facility costs
down," says Westphal. "We hope to get it to the point where we’re
at parity with what most grids are paying for conventional energy.
That’s really the end goal for all of the investor sets: the
utopia that you can put renewable energy projects in and it
doesn’t cost you any more money to build or run than a
conventional project."
How soon this will happen depends on who you talk to, Westphal says.
"Future projects will take advantage of new technologies, which are
rapidly developing—changing practically from month to month," he
says. "For example, if Jacksonville Electric wanted us to duplicate the
project we just completed, we would probably be looking at different
inverters, even from the same manufacturer, because they are
continually upgrading their product line. And that’s a good
thing. We constantly have to keep up with new developments in the
industry."
In short, part of being successful in the future is staying flexible
and being able to take advantage of what a constantly-evolving industry
has to offer. That, it turns out, is one of the things PSEG does well.
"We’re a pretty progressive company," says Westphal. "Ralph Izzo,
our CEO, said early on that climate change was really the pre-eminent
challenge facing the industry and because of that, we got into this
business to look for alternative means of generating electricity
without relying so heavily on fossil fuels."
And that’s why they are sprinting ahead.
March/April 2011
|
|