
With the global market for turbines, and demand easily outstripping supply, companies
such as PPM Energy are planning projects years in advance and lining up construction
schedules with turbine delivery schedules two or three years down the road.
Grassroots Approach to Wind Energy
PPM Energy’s grassroots approach to getting approvals for wind farm projects has
paid off, with recent projects—Big Horn in Washington and Klondike III in Oregon—getting
an encouraging thumbs-up from local governments and residents.
By Paul MacDonald
It’s a good thing PPM Energy’s Ty Daul likes coffee. Daul was the project manager for PPM Energy’s Big Horn
wind power project—he is now vice president of renewable business development at
the company—and spent a lot of time drinking coffee in farm kitchens in southern
Washington State. He was there to explain to farm families what the Big Horn project
was all about, and the benefits it would bring to the small community of Bickleton.
Daul’s grassroots approach, and the efforts of other PPM representatives, paid off
as the 200 megawatts (MW) Big Horn project got the go-ahead, was built, and started
sending power on to the grid, via Bonneville Power Administration transmission lines,
late in 2007.
The entire capacity of the Big Horn project and its 133 GE Energy 1.5 MW turbines
has been contracted to MSR Public Power Agency. MSR is a joint agency made up of
the Modesto Irrigation District, the City of Santa Clara and the City of Redding,
all in California.
This little corner of the Pacific Northwest is not new to PPM. Big Horn sits across
the Columbia River and about 25 miles from the company’s existing Klondike wind
power projects in Oregon. The Klondike III wind project near Wasco, Oregon became
operational in 2007 and generates 221 MW of electricity.
“Our interest in this area of Washington and Oregon goes back to when PPM Energy
was starting to build up a business to do greenfield development, and build projects
for ourselves,” says Daul. “This was one of the many areas we started looking at—it
was an area with good transmission capacity, good wind and open space.”

On the Big Horn project, PPM Energy worked closely with local
authorities and citizens to address concerns about the possible impact of Big Horn on the bird population—the nearby community of Bickleton is known as the bluebird capital of the world. PPM partnered with the community to build and place more
than 250 bluebird boxes around Bickleton, as a show of support for the community.
The Big Horn site is similar to the Klondike site just across the river, though
not identical. “They correlate fairly closely, but they have different elevations,
with slightly different drivers with the wind in each location,” says Daul. “On
a macro level, the wind is driven by similar elements, but on a micro level, you’ll
see the differences.”
The more recent projects—Big Horn and Klondike III—are considerably larger than
the earlier projects, Klondike I (at
24 MW) and Klondike II (75 MW). “Size is driven
by a lot of factors,” Daul says. “It’s driven by the turbines that might be available,
by what you can permit, and a large part of a project is driven by what you can
interconnect with the existing transmission grid. And, of course, customer demand.”
Capacity can oftentimes evolve with PPM projects, he notes. With a number of moving
“parts” going forward in parallel, it’s good to stay flexible. “With those factors
at work, and because these projects can take two to three years to develop before
we can even start construction, we take a good educated guess on where we think
the project is going to be in terms of size. But things move around a bit. One of
the factors that influence the project size may take longer to mature—or not even
be there. You may plan on 300 MW but then find out through the transmission study
that they can only take 200 MW.”
In the case of Big Horn, it was permitted for 250 MW, and they had land for that
amount of wind power generation. But they could only obtain an interconnect for
200 MW. “We are currently finalizing plans for that further 50 MW—in an ideal world,
all of that would have come together at once, but sometimes it doesn’t come together
as you planned.”
Daul notes that a number of the company’s projects have been phased, with capacity
added on later. For example, the company acquired Klondike I as an operating asset,
then developed Klondike II and, as mentioned, is currently building Klondike III.
It would make the most sense to max out the power that could be generated on sites—and
achieve economies of scale in terms of construction resources—through doing all
the work at once. But PPM Energy has plenty of company in the wind power industry
in not having access to all the resources—such as turbines—to do that.
“There are limited turbines out there, so as a company we have to allocate them
across the U.S. to different projects. It’s not a situation of always being able
to fit the most megawatts on every single project—we still have to satisfy customers
in other states.”
In addition to the solid support of Washington State, PPM’s Big Horn also had lots
of support from Klickitat County, and, thanks in part to all the coffee meetings
Daul attended, the support of local residents. So much so that PPM Energy is considering
further wind power projects in the area.
The front end work, with meetings and approvals,
went fairly smoothly, though their
construction schedule turned out to be quite aggressive, due to some bad weather.
“In terms of overall timing, from when you start moving dirt and building road until
when you get the turbines operating, it’s usually a six- to eight-month process.
Sometimes it’s a bit less, sometimes a bit longer, depending on the size of the
project and conditions.”
The Big Horn project was built during the winter months, to optimize the use of
their construction crew, and to time it with the delivery of turbines. At times,
however, the construction crew probably felt they were better off building an ark
than wind towers; they got hit with the worst rains in 30 years.
“We were able to manage through it,” says Daul. “It caused a bit of a delay, but
in the end, our construction team did an outstanding job and still delivered the
project close to on schedule and on budget.”

The entire capacity of the Big Horn project and its 133 GE Energy 1.5 MW turbines has been contracted to MSR Public Power Agency, a joint agency made up of the Modesto Irrigation District, the City of Santa Clara and the City of Redding, all in California.
While some areas of the region were hit with flooding, that was not the issue with
the Big Horn site; most of the land in the area is made up of basalt, with two to
three feet of soil on top. The heavy rainfall did not create puddles. “It just became
this big, wet, slushy mat on top of the rock,” says Daul. “The problem was getting
trucks in and out and moving heavy equipment around. Sometimes equipment got stuck
and a lot of times we just waited until the water drained off.” At one point, they
effectively shut the Big Horn project down for a month due to the impact of the
wet weather.
PPM usually acts as the general contractor on its wind projects—subbing out project
components such as electrical, civil and installation—and this pays off when there
are delays. “We have the in-house expertise to be the general,” says Daul. “We’ve
made a conscious decision to move in that direction to manage costs a little bit
better. But it
also allows us to better manage the portfolio of projects that we
have under construction.
“So if we have a problem, like we did with Big Horn and the rains, we just shift
our resources. We moved people down to another project we were building down in
Oregon where we did not have nearly as significant a rain issue. If we were not
the general contractor, we would not have that kind of flexibility or it would cost
us significantly more to do those kinds of workarounds.” He adds that it also gives
them more control over the subs hired on a job, which dovetails nicely with their
efforts to hire locally, wherever possible.
One of the big drivers in project scheduling—if not the biggest—is the delivery
of the turbines. With the global market for turbines, and demand easily outstripping
supply, companies such as PPM are planning their projects years in advance, and
lining up construction schedules with turbine delivery schedules two or three years
down the road. It has reached the point that key suppliers such as Mitsubishi and
Suzlon are involved with PPM Energy projects at the engineering phase.
“We’re way out ahead,” says Daul. “The way PPM views it, turbine companies and contractors
aren’t just suppliers—they are strategic partners. We have a contractual relationship,
but we view it that we are going to be working with these companies for two, three,
four years or longer. We need to make sure we’re working together and getting things
right.”
To that end, PPM Energy has signed long-term supply contracts with several turbine
suppliers. This past June, Suzlon Wind Energy Corporation, the U.S.-based subsidiary
of Suzlon Energy A/S of Denmark, extended its contract with PPM to add 300 MW of
wind turbines. It has been touted as one of the largest single contracts in the
history of Suzlon and the U.S. wind energy industry.
The original agreement called for delivery of 300 MW of turbine capacity in 2008
and 100 MW of capacity in 2009. It has now been extended to include an additional 300 MW in 2009 for a total of 700 MW over two years. And Mitsubishi Power Systems
has finalized agreements to supply 169 of the company’s flagship MWT92/2.4 wind
turbines to PPM Energy wind projects in the U.S. This 405 MW order includes wind
turbines to be installed at various PPM project sites in 2008 and 2009.
Of course, being part of international wind energy giant Iberdrola, with its clout,
also helps. Iberdrola bought out PPM Energy and its parent company, Scottish Power
last year.
There are constraints beyond the supply of wind turbines. “It’s getting to the point
that we also have to schedule a year or two in advance for cranes,” adds Daul. “It’s
not just the construction of wind farms that is driving this—there’s all kinds of
construction in the U.S. and globally that are keeping the demand high for these
kinds of resources.”
PPM Energy is doing what it can to exercise control, from making advance crane commitments
right through to managing the purchase of what are becoming longer lead items, such
as cabling and transformers.
“It’s not just costs we are trying to control,” says Daul. “It’s also the schedule,
as well as quality. If you’re at the end of the line, and are buying the last available unit of something, sometimes you can be looking at components of questionable quality.”
And there are also human resource issues the industry is grappling with, with companies
in competition for wind power talent. Daul says that PPM Energy works hard to create
the right corporate culture to attract and retain people. “It’s not just about
compensation, which is obviously a factor. It’s the type of people you are working
with, the opportunities, the ability to have decision making and control in what
you are doing.”
One thing that he believes sets PPM apart is their approach towards the environment.
“I really feel we are setting the bar for others to follow. We go above and beyond
what is required.”
In the case of Big Horn, they worked closely with local authorities and citizens
to address concerns about the possible impact of Big Horn on the bird population—Bickleton
is known as the bluebird capital of the world. Although bluebirds are common at
wind project sites, they are not at high risk. PPM’s studies indicated the turbines
will not hurt the bluebird population, which generally flies well below the blades—and
that has proven to be the case.
PPM also partnered with the community to build and place more than 250 bluebird
boxes around Bickleton, as a show of support for the community.
Daul also cited a project they are doing in Texas. “Texas siting regulations, if
there are any, aren’t very defined. But we follow the same process and procedures
as we would in an area that requires very stringent monitoring and field studies.
“From our standpoint, we want to make sure what we are doing fits with the community.
We are going to be there for a long time.”
With all their wind projects, including Big Horn, they work to minimize the footprint.
At Big Horn, canyons run through parts of the 15,000-acre site. When company officials
met with local environmental groups, the groups said that some turbines were sited
quite close to the canyons and asked if the company would be willing to move them
back.
“We did that voluntarily,” says Daul. “We don’t have infinite flexibility to do
those kinds of things, but we will definitely work with landowners, county agencies
and environmental advocates to see how we can best fit a project in an area.”
Out of that 15,000 acres, he notes, only about one percent, or about 150 acres,
has been taken out of permanent land use. In addition, the company has also set
up a 455-acre habitat south of the site.
Taking an environmental approach is not only a hit with the locals—power customers
also like it. “Customers say they want windpower, but they want windpower from sites
that have been developed in a responsible way.”
Moving forward, Daul says he believes the industry is likely to see more single-phase
wind power projects, rather than multi-phase, such as Klondike, or projects with
capability add-ons, such as Big Horn. “I think we’re going to continue to see some
small projects, but the trend seems to be towards larger projects because of the
economies of scale. And longer term, some of the best wind resources are in areas
where there are going to have to be significant transmission fixes—spreading out
the cost of those
upgrades will require bigger projects.”
He notes that some of the richest wind resources in the country, in states such
as the Dakotas and Wyoming, are also the furthest away from significant loads, “We’re
going to have to address that with transmission capacity to these states if, as
a nation, we really want to tap into this renewable energy resource.”
Return